Rennes railway station: removal of demolition rubble

Image
Evacuation de déblais de démolition - Gare de Rennes

Specifications:

Conveyance of materials from platform demolition prior to station reconstruction. Desired throughput 50 To/h and grain size: 0/150 mm.

Problem :

Evacuation of demolition rubble from the platform access tunnel and stockpiling outdoors at a height of 9 m. Conveyors placed in the tunnel under the tracks had to be mobile to maintain access to the docks. Regulated and limited worksite duration.

Our solution:

Rental of two movable, wheel-mounted MANUBLOC E.A 25 m x 500 Belt Conveyors. Cascade operation to a MANUBLOC E.A 18 m x 500 steerable stacking conveyor with load pick-up goat. Stacking height: 9 m

  • Preparation time: 3 weeks
  • Delivery time: 2 months
  • Site location: France