Land decontamination project

Terms of reference

As part of a decontamination project, the requirement was to transfer soil from one side of a road to the other. The desired throughput was 300 to/h.

The installation had to be erected at night for safety reasons due to traffic stoppages.

Our solution:

Implementation of a large-volume feed hopper and a 75-meter road crossing with a footbridge. This eco-responsible solution was very much appreciated and validated by the municipality, as it avoided a truck transfer that would have generated increased traffic and high Co2 emissions.

  • Preparation and installation time: 2 months
  • Rental period: 18 months