Evacuation of materials by barge on a lake in Switzerland
Request:
Evacuation of earthmoving materials by barge. The volumes to be handled were 70,000m3 and the desired flow rate 80m3/h.
Problem :
Handling of excavated material from the banks of a lake to fill barges. Securing a public passageway under the Belt Conveyor. Significant overhang due to installation of the loading facility on the bank. Passage of site machinery for loading directly into barges. Large particle size (0/350 mm) and clogging product.
Our solution:
Installation of a handling system with a main conveyor equipped with a goat and recovery cables to evacuate materials by barge. Motorized conveyor head equipped with a flow management chute with flexible rubber sleeve. Belt Extractor allowing the passage of coarse-grained bales and facilitating the removal of sticky products. Drawings for configuration, civil engineering and assembly. Supply of a feed hopper, 1 Manuextract and 1 used Manukit E.A 35 m x 650 mm Belt conveyor.
- Preparation time: 3 weeks
- Rental period 64 weeks
- Site location: Switzerland