Hydroelectric plant: 150,000m3 of spoil transported over 200 metres

Image
Transporteur à bande pour usine hydraulique

Request :

Transport of earthmoving materials to the La Bathie hydroelectric plant (73). The volume to be handled is 150,000m3, with a desired flow rate of 250 m3/h (7,000 m3/week).

Problem :

The handling system passes under a railroad line and over the access road to the hydroelectric plant; the stacking conveyor is located under a high-voltage line. The entire handling line must be covered. Variable and potentially large granulometry (0/500 mm).

Our solution:

Implementation of a 200-metre handling system, including configuration, assembly and civil engineering drawings. Provision of a feed hopper, 1 Manuextract, 3 MANUKIT 800 Belt Conveyors (180 meters), 1 Manukit E.A 20 m x 800 mm stacking conveyor (motorized orientation). Plant capacity is 300 m3/h.

  • Preparation time: 6 weeks
  • Rental period reduced from 22 to 16 weeks (9400 m3/week)
  • Site location: France