220m of conveyor belts on the Le Brassus site in Switzerland

Image
Construction d'usine - évacuation de terre

Orllati project for Audemars & Piguet

Project specifications and challenges:

As part of the construction of Audemars & Piguet's new production unit, implementation of a handling line behind the passenger station to transport earth and rubble from the construction site. Evacuation by rail at a rate of 300 to/h.

Our solution:

Installation of a 41-meter-long roadway to reach the conveyor line behind the Passenger Station. Feeding via a hopper and an Extractor, total handling length: 220 meters.

  • Preparation and installation time: 2 months
  • Rental time: 5 months